Schedule

The Schedule board shows every machine, person and tool in a row, with time running across. Each work order stage sits on it as a block, so you can see what is running when, where the gaps are, and which runs will miss their date. You also plan and re-plan a work order from here.

5 min readYou need: view access to Booking; work order edit access to plan or re-flowBefore you start: resources and a working calendar are set up, and the work order has stages
Video coming soon: The Schedule board in 2 minutes

Where it fits​

Work Order Process (the route)Work orderSchedule (plan the stages)Release and startRun on the floor

A work order carries the stages of its route. Planning puts each stage into a working shift on the machines and people it needs. The board is where you read the result. It is not a place to place a single stage by hand: the plan always lays out a whole route.

Quick plan​

About 1 minute
  1. Go to Production › Schedule.
  2. Click the filter icon above the board (Show filters) to open the filter bar.
  3. In Plan a run, pick the work order.
  4. Leave Back from the due date chosen and enter the Due date.
  5. Click Schedule.
  6. Open one of the new blocks to check where it landed.

Done. The run's stages appear on the board as dashed blocks, and the run is marked if it is planned to finish after its due date.

Video coming soon: Plan a run in under a minute

Full guide​

Read the board​

Each row is one resource. Its name, kind and code are on the left, with how much of its working time is used and how that splits between planned and worked. Time runs left to right.

  • Rows are your active resources at one location. The kinds are Machine, Work Centre / Facility, Operator / Labour and Tool.
  • Columns are hours when you look at two days or fewer, and days for anything longer.
  • Grey stretches are closed time: outside the resource's working hours, a holiday or a shutdown, from its working calendar. Point at one to see which.
  • Blocks are what occupies the resource. Production blocks have one colour per work order. Set-up / Changeover, Maintenance, Leave, Breakdown and Other have their own colours.
  • A dashed, faded block is planned and has not been worked yet. A solid block is time that was actually worked.
  • A flagged block belongs to a run that is planned to finish after its due date.
  • Set-up / Changeover blocks are booked when you plan a run whose process stage has a resource set to Set-up only.
  • Free capacity is an empty stretch inside working hours.

A legend sits above the board. A line above the filters names the time zone the board is drawn in. It is the plant's working calendar zone, not your computer's clock. A resource that works to a different zone says so under its name.

At the bottom, the board totals the resources shown and the planned time in the window, split into worked and not yet worked.

Filters and range​

The filter bar starts folded. Click the filter icon (Show filters) to open it, and again to fold it away. The Plan a run and Re-flow a run pickers are in it too. The board opens on today and the next six days.

Fields in this section
FieldWhat it does
From, ToThe dates to show, up to 62 days. A range that ends before it starts is refused with a message.
LocationWhich factory or site to show. Only offered when your business unit has more than one. The board remembers your last pick.
ResourceNarrow to one resource, or leave on All resources.
ShowTurn Machine, Work Centre / Facility, Operator / Labour or Tool rows off and on.

Active filters that differ from the default appear as chips above the board. Reset brings back the default week, all resources and all kinds. There is no search box on the board.

Open a block​

Click a block to open the Schedule entry panel beside the board. It shows:

  • The entry number, its status (Planned, Running, Completed or Cancelled) and what it is for.
  • The planned dates, the planned time, the time logged, the variance, and any planned time outside working hours.
  • The recorded work, each stretch with its start and end, or Nothing recorded against this entry.
  • The cost recorded, if you have access to production costing.
  • Which run it belongs to, with Open run to go to that work order.

If the block belongs to a work order, the route of that run opens above the board too. It shows the run's number, status, how it was planned, its earliest start and latest finish, and each stage in route order. Stages that run side by side are shown together, with both the working time added up and the calendar time they take. If the run is planned late, a note says by how much. Close either with the x.

Plan a run​

There are two ways to plan from the board, and one more way to re-plan. You need edit access to work orders to see them. A run can be planned when it is a Draft, In Review, Open or In Progress and has at least one stage.

  1. In the filter bar, open Plan a run and pick the work order. The list shows runs that can be planned. Or open a block, and use Plan on the run route.
  2. Choose how to plan:
    • Back from the due date: enter the Due date (the last stage finishes by the end of the last working shift on that day). Optionally enter Not before to stop the plan starting earlier. Bizconnekt works out when the run must start. A route that will not fit is refused.
    • Forward from a start: enter Starts at, or leave it empty. Bizconnekt works out when the run finishes. If that is past the due date, the plan is still saved and flagged.
  3. Click Schedule (or Plan forward).

Each stage lands inside a working shift and claims the machines and people it needs. The message tells you how many stages were scheduled and how many claims were booked. If the plan finishes after the due date, you see by how much and the plan stands.

Planning a run that is already planned releases its old claims and books new ones. The same Schedule action is on the work order's row menu. See Schedule and Re-flow.

Re-flow a run that slipped​

Use Re-flow when a run is In Progress and the shifts have not gone to plan. It re-plans only the stages that are left, against what the run has actually made. Finished stages, and running stages that have made their planned quantity, stay as they are.

  1. In the filter bar, open Re-flow a run and pick the run. Or open one of its blocks, and use Re-flow on the run route. Only runs In Progress are offered.
  2. Enter Pick it back up at, or leave it empty to re-plan from now.
  3. Click Re-flow, then Release and re-place to confirm. The plan the remaining stages hold is released and booked again where the work now lands.

Re-flow never happens by itself. A short shift does not move anyone's plan until you re-flow.

What the board will not let you do​

  • Drag or resize a block. The board is read only. Moving work means planning the run again.
  • Place one stage on one resource. Planning always lays out the whole route.
  • Add maintenance, leave or breakdown blocks. There is no form for them anywhere in the app, on the web or on mobile.
  • Double-book a resource. A resource cannot be claimed for two things in the same slot. If it has several identical units (see Capacity Units in Resources), that many can share a slot.
  • Plan a run with no stages. Plan is greyed.

Export, import and print​

The board has no export, no import and no print. To keep a record of a run, print its run sheet from the work order.

Who can do what​

You want toWhat your role needs
Open the board and its blocksView on Booking
See the run route and the late flagsView on work orders, as well as Booking
Use the Plan a run and Re-flow a run pickers, or plan or re-flow a runEdit on work orders, as well as Booking
See the cost recorded on a blockAccess to production costing

Without view access on Booking the Schedule row is not in the sidebar and the page says you have no access.

On mobile​

The mobile app has a Schedule tab, read only. It shows one week at a time: step to the previous or next week, or go back to this week. Choose a location if there are several, then tap a day. Each day chip says how many entries are booked. Below it, each resource lists its entries for that day with the time, and a tap on a production entry opens the work order if you have access to work orders. Pull down to refresh.

You plan a run on the phone from the work order. Its actions menu has Schedule and Re-flow with the same choices as the web.

The mobile Schedule has no filters other than location, no chart of time across the day, and no panel for a single entry.

Same on iPhone and Android. The Android app is on Google Play. The iPhone app is coming soon to the App Store.

Problems and fixes​

The board says "No locations to schedule"

The board groups resources by the factory they sit at. Add an address to this business unit, and give each resource a location in Resources.

"Nothing scheduled"

Either no resources match these dates, or every kind is hidden. Add a machine, operator or work centre, widen the dates, or turn a kind back on in Show.

"A board covers at most 62 days"

Pick a shorter range with From and To.

"Plan a run" or "Re-flow a run" is missing, or the list is empty

You need edit access to work orders. The list shows only runs that can be planned, and the Re-flow list only runs In Progress. "No run to plan" and "Nothing is running" mean there are none. A long list is cut: plan the others from the work order.

The plan was refused

For a plan back from the due date, the route may not fit before that date. Move the due date later, remove Not before, or plan forward and read where it finishes.

A run is flagged late

The plan finishes after the run's due date. Open any of its blocks to read by how much, then plan it again with an earlier start or a later date. The flag is shown for the runs in the planner list only.