Production Setup
Setup is where you tell Bizconnekt what your plant has: the working week, what your people and machines can do, the machines, people, work centres and tools themselves, and what an hour of each costs. You set it up once. Production planning and costing then use it.
Video coming soon: Production Setup in 2 minutesWhere it fits
Open Production › Setup. The four steps sit in a row along the top of the screen, in the order a plant is set up: each one builds on the one before it. A step shows a tick once it has at least one record. Hover over a step for a one-line reminder of what it is for. You only see the steps your role gives you access to.
What you can do
The four kinds of resource
A resource is anything a stage of a job needs a slot of time on. You pick one of four kinds when you add it.
| Kind | What it is | Example |
|---|---|---|
| Machine | A piece of equipment that does work. | A lathe, a moulding press, an oven |
| Operator / Labour | A person, or a pool of interchangeable people. | A welder, the finishing crew |
| Work Centre / Facility | A place where work happens. | The paint booth, Bay 3 |
| Tool | A tool, die, jig or fixture. | A die, a mould |
There is no separate work centre screen. A work centre is a resource of the kind Work Centre / Facility.
When you really do have several of the same thing
Give a resource a Capacity of 1 for one machine or one person. If you have three interchangeable units, such as three identical moulds, add one resource with a Capacity of 3. A person who is named as an employee on a resource always has a Capacity of 1.
How Setup is used
- Skills are matched to the stages of a Work Order Process. A resource can only hold skills of its own kind.
- Calendars decide which hours a resource is open. A resource with no calendar of its own follows the default calendar.
- Planning a run uses your resources and calendars to put its stages on the Schedule. If a process stage names a resource as set-up only, the set-up time is booked for you when the run is planned. The board only shows the plan: you cannot drag blocks on it, and you cannot book maintenance, leave or breakdowns on it. See the Schedule page for what the board does.
- Rates put a cost on the hours a resource is used.
Who uses it
Plant managers and planners set it up and keep it right. Schedulers read it. Each screen has its own access level, so a scheduler can see the machines without seeing what people are paid. Resource Rate has a separate access setting from Resources.
On mobile
The mobile app has no Setup screens. Set up calendars, skills, resources and rates on the web app.
Same on iPhone and Android. The Android app is on Google Play. The iPhone app is coming soon to the App Store.